“Engaged to completely refurbish Box Hill aquatic centre over a two year period, required collaborative planning between OTD and council to set up the project in stages to minimize the disturbance to its members.
Completing the outdoor 25mt pool in 2022 meant patrons were still able to use the facilities when the works continued inside in 2023. Toddlers pool and splashpad were completed next and then the dive bowl and lap pool followed. Completed on time for the reopening and lessons the centre management , staff and council were delighted with the finished result.”
Other works completed:
• Refurbishment of the change room facilities
• Replacement of the dive tower
• Replacement of stainless fittings
• Balance tank relining